Before you automate: a simple time-and-motion study for SMEs

Automation projects tend to start with a demonstration. A robot arm folds a carton in eleven seconds; a supervisor says the same job takes forty minutes on the floor. Both numbers sound persuasive, and neither survives contact with the shop. Before committing to automation, robotics or digital transformation, a short time-and-motion study gives you an honest baseline: how long the task genuinely takes, who waits for whom, and which steps a machine could realistically take over.

The method is older than the software and needs almost nothing: a stopwatch, a clipboard, a shift roster and a quiet spot near the line. Its value is not academic rigour but credibility, because it replaces assumptions with observations your own operators recognise. It also exposes what sales decks leave out: setup, changeovers, rework, fetching trolleys, waiting for a forklift. Those variables decide whether payback arrives in two years or eight.

For Australian manufacturers, food processors, warehouses and service businesses, the numbers are unusually sensitive. Award wages and penalty rates, 12 per cent superannuation, thin margins on imported inputs and a shortage of skilled technicians all push the same way: small efficiency gains matter, and a badly specified machine can drain a small business faster than it pays back. This guide sets out a study you can run in a fortnight, and shows where the Shinagawa City automation and robotics programme, which matches local firms with vetted technology providers and offsets implementation costs with subsidy support, fits into the next step.

Why a baseline beats a guess

A time-and-motion study breaks a process into steps and records actual elapsed time rather than standard time. For a first automation assessment you need only the simple version: elapsed seconds per cycle, cycles per shift, and observed waiting. This is not a formal industrial engineering exercise; it is a structured observation anyone on the floor can run with a stopwatch. The output is a baseline you can defend when a capital request sits on a table beside machinery quotes, software subscriptions and internal labour.

The study also shows where the labour actually sits. Manual handling, machine loading, labelling, palletising and end-of-line inspection look similar on a process map but differ wildly in cycle time and predictability. Tasks that are repetitive, consistent and physically demanding are automation candidates; tasks that swing with order mix or demand judgement are not. Recording how much a cycle stretches on a bad day matters as much as the average, because a machine sized to average output will starve on a busy morning and idle on a slow Friday.

Planning the study around a real shift

Pick one product family and one full shift. Australian plants often start early, with 6am lines in Melbourne's Broadmeadows and Dandenong or Adelaide's northern suburbs, so observe a properly crewed shift rather than a lonely hour after lunch. Check the roster first, because a study run on a reduced-crew day describes the wrong process. Ask the operator what usually varies — we wait for the forklift, the batch changes every two hours — since those answers shape the business case more than any spreadsheet.

Choose tasks that repeat many times per shift. A packing station completing forty cycles an hour gives forty usable data points; a bespoke engineering job completed once a week does not. Capture at least one changeover while you are there, because changeover time hides a surprising share of cost in small-batch Australian operations serving customers from Sydney to Perth.

Settle the observation rules before you start: what you will time, what you will ignore, and how you will note interruptions. Brief the operator and, where relevant, the health and safety representative so the exercise reads as an improvement study rather than a performance review. In customer-facing operations, where one counter may absorb foot traffic from overseas visitors, the same logic applies, and the Shinagawa programme's Japanese-language case study shows how observation rounds are structured in a Japanese operating environment.

Recording the work without interrupting it

Write every step in the order it happens, using action words: pick, place, scan, wait, walk. For each step, record elapsed time with a stopwatch or slow-motion phone video, count the cycles, and note who performs it. A simple spreadsheet with four columns — step, operator, elapsed seconds, cycles per shift — is enough for the first round. Consistency beats granularity, because an observer trying to time every finger movement will lose the shift.

Video needs rules. Under state work health and safety laws built on the Safe Work Australia model, changes to work methods and equipment involve consultation with workers and safety representatives, so footage should be agreed with the crew and framed as improvement evidence. Mask faces, avoid capturing customer conversations, and tell the people being filmed if your business is covered by the Privacy Act 1988 or a state surveillance and privacy regime. New South Wales and Queensland also expect psychosocial risk management, which is another reason to be open about why the recording exists.

Capture the surrounding variables while you are standing there: queue lengths, trolley trips, rework rates, machine faults, break coverage. Convert them into units the business can price later — labour hours per shift, units per hour, cartons handled, downtime minutes, metres walked.

Where Australian conditions change the numbers

Convert observations into money using the rate that will actually be paid. Start from the award or enterprise agreement rate under the Fair Work Act 2009, add the 12 per cent superannuation employer contribution, add payroll tax where you sit above the exemption threshold, and include penalty or overtime rates if the hours you observed attract them. A step that looks like a two-minute saving in a Queensland or Victorian workshop becomes real money once Saturday rates are applied. Use the rate you would have to hire, not the rate you would prefer to pay.

Remember the local market while you are at it. Most small and medium-sized manufacturers in Australian cities — family-run plants around Preston, Logan, Elizabeth or Osborne Park — compete on lead time and consistency rather than price, and rising input costs with 10 per cent GST on imported components leave little slack. That makes the study a hunt for value leakage, not simply a stopwatch exercise. If minutes disappear walking to a shared printer for a label, a digital workflow fix may outperform a robotic arm on cost and payback.

Incentives and legislation shape the final payback case. Small businesses with aggregated turnover below $10 million can generally write off eligible plant and equipment costing up to $1,000 per item immediately under the instant asset write-off, with larger assets depreciated over their useful life, and eligible research and development work may qualify for the R&D Tax Incentive, which for companies with aggregated turnover under $20 million returns a benefit above the corporate tax rate. Confirm your position with an adviser rather than a supplier, and check state energy and grant programmes before assuming support is unavailable.

Turning observations into an automation business case

Build the comparison simply. Multiply annual cycle count by observed seconds saved per cycle, value those seconds at loaded labour rate, then subtract the machine's running costs — energy, consumables, software licences, maintenance, and the hours your own staff will spend supervising it. A task running 100,000 cycles a year with eight seconds saved has clear arithmetic; two seconds on 500 cycles a year never repays a machine.

Then test the assumptions that could break the case: utilisation, changeover frequency and what happens when volumes fall. List softer benefits separately — fewer manual handling injuries, staff moved to higher-value work, consistent output, faster quoting for Australian customers — so the decision-maker can see which numbers carry the argument.

Before signing, read the programme's advice on navigating vendor lock-in, because protocols, spare parts and data ownership are settled before the purchase order rather than after it. Ask whether the integration depends on a single proprietary controller, whether process data can be exported in a usable format, and who services the system locally. In regional operations where the nearest robotics technician may be a flight away, local service capability can be worth as much as a headline cycle time.

A practical checklist before you commit capital

Two weeks of careful observation usually buys more certainty than a month of modelling. The Shinagawa City programme connects businesses with vetted automation and robotics providers, offsets implementation costs with subsidy support, and runs practical seminars on factory digital transformation, IT investment and online sales efficiency that give managers the wider context a factory project needs. Australian firms that supply into the ward or work alongside Japanese partners can join the same seminars and request a vendor introduction. Bring your baseline data to the first conversation, because once the room knows how many seconds a task really takes, the discussion moves quickly from possibility to payback.